Cherry Avenue construction - Southwest Gas Project

Release Date: 
05/16/2017 - 9:15am

Cherry Avenue construction: Southwest Gas Project

5/16/17

Please see the map below which corresponds to the work described below for the Southwest Gas pipe replacement project for Summer 2017.

Note - Dates could vary based on weather conditions.

Cherry Avenue North of Speedway - May 7, 2017 through July 31, 2017

  • All work North of Speedway will be performed at night from 6:00PM to 6:00AM
  • Mabel Intersection – BSRL Trailer to north curb of Mabel Intersection - May 7, 2017 through May 20, 2017
  • Cherry from HSIB Driveway entrance north to Drachman St. - May 22, 2017 through June 3, 2017
  • Cherry from Speedway north to Helen - June 3, 2017 through June 30,2017
  • Pressure testing of new gas line (Daytime impact just south of Drachman) - July 19, 2017 through July 21, 2017
  • Final Pavement Repair - July 24, 2017 through July 31, 2017

Speedway / Cherry Intersection (Bore across Speedway) June 5, 2017 through June 21, 2017

SPEEDWAY EAST AND WEST BOUND TRAFFIC WILL NOT BE CLOSED

Cherry Ave – South of Speedway May 15, 2017 through July 31, 2017

  • All work south of Speedway will be complete road closures.
  • South of Speedway to north curb of 2nd St. - May 15, 2017 through July 31, 2017
  • 1st Street / Cherry intersection – Complete closure - May 26, 2017 through June 9, 2017
  • Mill and overlay/sidewalk repairs - July 24, 2017 through July 31, 2017

If you have questions, please contact Chris Kopach, University of Arizona Facilities Management, ckopach@email.arizona.edu or 520-626-4919.