May 23, 2016

Preparation will begin for concrete placement of the 1st floor deck.

May 10, 2016

Placement of concrete foundations and walls and installation of underground electrical & plumbing systems will continue

May 2, 2016

Installation of a construction barrier within the Keating BIO5 Building will begin on Saturday, May 7th

April 25, 2016

Basement foundation continues.

April 18, 2016

Placement of concrete foundations and walls continues. Installation of waterproofing at the elevator pit walls will occur this week. Installation of underground electrical will start the week of April 25th.

April 11, 2016

The South Tower Crane was erected last weekend. The new tower crane will handle the heavy lifting until December.

April 5, 2016

Installation of shotcrete walls continues on the North Elevation. Reinforcement is being installed and concrete footings are being placed for the basement throughout the site. The south Tower Crane will be erected April 8th and 9th. Pedestrians, Bicycles and cars will be detoured along Warren or Cherry as shown in the newsletter (pdf).

March 28, 2016

The South Tower Crane will be erected on April 8th and 9th - Helen will be closed between Cherry & Warren both days.

March 7, 2016

Concrete will begin Wednesday, March 9th and continue in the basement for four months. Drilling of rebar dowels into the Keating basement will begin on March 14th with a low-noise drill. The tower crane will arrive in early April.

February 24, 2016

A new map providing an overview of current and future UA and Banner construction projects is now available. Underground electrical and plumbing starts this week. Soil nail shoring and excavation complete.

February 23, 2016

BSRL Food Service Survey http://studentvoice.com/az/biosciences2016

February 17, 2016

Beginning on February 22nd the intersections of Cherry & Mabel and Cherry & Helen will both become 4-way stops. Excavation activities to finish this week.

February 8, 2016

Speed Limit on Cherry Ave. revised to 15 MPH. Soil nail shoring and excavation continues.

February 1, 2016

Concrete placement for foundations will start early March.

January 25, 2016

Excavation will continue this week through the month of February.